Production
Production rate
Tonnes per hour, day and shift from machine speed, grammage and trim width.
Share of time actually producing saleable paper
Net rate
3.17t/h
- Gross rate (100% time)
- 3.44 t/h
- Per 12-hour shift
- 38.0 t
- Per day
- 76.0 t
How it's calculated
t/h = speed (m/min) × grammage (g/m²) × width (m) × 60 ÷ 1 000 000, then × time efficiency.